ASSESSMENT OF MANUAL HANDLING TASKS BASED ON KEY INDICATORS Version 2001
Workplace/Activity:
--Holding (> 5 s)
Total duration at working day Time rating points
1st step: Determination of time rating points (Select only one column !)
1
Lifting or displacement operations (< 5 s)
Number at working day Time rating points
Carrying (> 5 m)
Overall lenthg at working day Time rating points
< 10 10 bis < 40 40 bis < 200 200 bis < 500 500 bis < 1000 ≥ 1000
1 2 4 6 8 10
< 5 min 5 bis 15 min 15 min to < 1 hr 1 hrs to < 2 hrs 2 hrs to < 4 hrs × 4 hrs
1 2 4 6 8 10
< 300 m 300 m to < 1km 1 km to < 4 km 4 to < 8 km 8 to < 16 km ≥ 16 km
1 2 4 6 8 10
Examples: • laying bricks, • placing workpieces into a machine • taking boxes out of a container and puttung them onto a conveyor belt
Examples: • holding and guiding a cast iron slug while working on a wheel stand, • operation a hand grinding machine, , • operating a weedeater
Examples: • furniture removalt, • delivering scaffolding parts to a building site
2nd step: Determination of rating points of load, posture and working conditions
2.5
Effective load for men < 10 kg 10 bis < 20 kg 20 bis < 30 kg 30 bis < 40 kg ≥ 40 kg
1)
Load rating point
Effective load
1)
for women
Load rating point
1 2 4 7 25