Patologia dos pavimentos rígidos
INTRODUÇÃO………………………………………………………………………………………………………………………....2
DADOS DE EMPREITADA……………………………………………………………………………………………………….…3
ACTIVIDADES REALIZADAS………………………………………………………………………………………………………5
SEGURANÇA E HIGIENE NO TRABALHO………………………………………………………………………………….6
EQUIPAMENTOS E MEIOS HUMANOS…………………………………………………………………………………….6
PLANO DE TRABALHO……………………………………………………………………………………………………………...7
MAPA DE CONSTRAGIMENTOS……………………………………………………………………………………………….8
MAPA DE INCONFORMINDADES…………………………………………………………………………………………….9
RELATÓRIO TÉCNICO………………………………………………………………………………………………………………10
MONITÓRAMENTO E SUPERVISÃO……………………………………………………………………………………….11
GRAFICOS……………………………………………………………………………………………………………………………….12
PLANO DE TRABALHO COM OS TD REGISTADOS…………………………………………………………………….14
CÁLCULO DO IADRO……………………………………………………………………………………………………………….15
CARTAS E PARECES EMITIDOS….………………………………………………………. ……………………………………16
CONCLUSÃO……………………………………………………………………………………. …………………………………….17
MAPA DE AUTO MEDIÇÕES………………………………………………………. ………………………………………..…18
ANEXO (FOTOS ILUSTRATIVAS) ………………………………………………………………………………………………19
1) INTRODUÇÃO
Tendo como factor principal o controle da qualidade global da empreitada, é objectivo deste relatório informar a vossa Exma. sobre o estado das actividades em execução, no mês de Agosto, não deixando de referir as situações relacionadas com o mau andamento das actividades no decorrer da empreitada, tais como atrasos resultantes de constrangimentos ocasionais, atraso na entrega de materiais, razões de ordem climatéricas, o grau de cumprimento do plano de trabalhos, autos de medições, eventuais notificações de ordem relatadas de forma clara e sucinta, sempre respeitando a deontologia exigida pelas normas e regras estabelecidas pela lei 20/10.
2) DADOS DA EMPREITADA
3) ACTIVIDADES REALIZADAS
1 – Descofragem de pilares – 513 m2
2- Cofragem em vigas – 462,5m2
3- Colocação de armaduras em vigas – 146 Ton
4-