Programação da produção-sob-encomenda utilizando pert-cpm
Fernando Ribeiro de Melo Nunes - MSc
Professor Adjunto IV - Universidade Federal do Ceará - Fone : ( 085 ) 288 9635
Oscar Luiz França de Paula - Especialista em Eng. de Produção
Gerente de Montagem da Sangati-Berga - Fone ( 085 ) 239 3984
Alexsandro Amarante da Silva - Engº Civil
SRO / 10a RM - Fone ( 085 ) 267 5110
Abstract This paper shows an application of the technique of the PERT/CPM as a tool to program the production, on an order based company that produces machines for wheat industrialization. The scope of their production line is 80 different machines, each with 5 or 6 models of different sizes and power. The orders with an average of 4 different machines are delivered only when complete. The main problems are to keep all sections of the plant full and to deliver the orders on time. The soluction was made possible with the use of the softwear MS-Project 4.0 over the flux of operations and times for all machines, and the use of PERT/CPM to sequence jobs on work stations, having as target to deliver on time all orders Key words : Programming, Production to Order, PERT/CPM.
1. Introdução As empresas que trabalham com produção-sob-encomenda, caso típico dos fabricantes de máquinas especiais, têm grande dificuldade em sequenciar a produção, visando conciliar a ocupação e produtividade dos equipamentos, com os prazos de entrega dos clientes. Sem uma programação global, fazer uma venda com prazo de entrega fixado é como atirar no escuro. São produtos distintos, com fluxos de produção os mais variados, passando por um conjunto fixo de máquinas e operários. Este trabalho foi desenvolvido para resolver o problema de um fabricante de máquinas para moinhos de trigo. Sua linha de produtos tem 80 máquinas diferentes, cada uma com 5 a 6 modelos onde variam dimensões e capacidade produtiva.
2. Objetivo Sequenciar os trabalhos nas máquinas visando a otimização do tempo disponível, e possibilitar a